Considering today as end of day 7 develop a gantt


Considering today as end of day 7, Develop a Gantt scheduling chart for the activities below:

Scheduled day to begin Job A was day 3 and supposed to take 6 days. Job A is 1 day ahead of schedule.

Scheduled day to begin Job B was day 1 and supposed to take 4 days. Running as per schedule.

Scheduled day to begin Job C was day 7 and supposed to take 2 days. The job was started on day 6.

Scheduled day to begin Job D was day 5, but was delayed until day 6 and supposed to take 3 days.

Scheduled day to begin Job E was day 4 and supposed to take 5 days. The job started on time but fallen behind 2 days.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Considering today as end of day 7 develop a gantt
Reference No:- TGS02433210

Expected delivery within 24 Hours