Consider the WBS shown below:

1.00.00
1.1.0
1.1.1
1.1.2
1.2.0
1.2.1
1.2.2

If the total program costs $100,000 and 1.2.1 and 1.2.2 are each $20 K, then the cost of 1.1.0 is:

Answer

$20 K

$40 K

$60 K

Cannot be determined