Consider the set of activities duration in days and


consider the set of activities, duration (in days), and predecessors for a project given below.
Activity A B C D E F G H I J K
Duration 9 12 3 4 5 9 8 3 6 9 1
Predecessors - A A B,C C B D F,D G H,I E

a) Develop a network diagram representation for the project.
b) Determine the critical path.
c) Determine he float time for all activities that are not on the critical path.

Request for Solution File

Ask an Expert for Answer!!
Electrical Engineering: Consider the set of activities duration in days and
Reference No:- TGS0613068

Expected delivery within 24 Hours