Consider the following three-step assembly operation with


Consider the following three-step assembly operation with quality problems. All resources are staffed by one employee.

  • The first resource has a processing time of 7 minutes per unit.
  • The second resource has a processing time of 6 minutes per unit.
  • The third resource has a processing time of 5 minutes per unit. With a 40% probability, the flow unit coming out of the third resource has to be reworked. In that case, the operations at the second and third resources are repeated. You can assume that (a) rework always succeeds (i.e. a unit going through the rework loop will always work after the third resource),and (b) the processing times for units in rework are the same as for regular units.

For every unit of demand, how many units have to flow through the second step in the process?

Solution Preview :

Prepared by a verified Expert
Mathematics: Consider the following three-step assembly operation with
Reference No:- TGS01564194

Now Priced at $30 (50% Discount)

Recommended (92%)

Rated (4.4/5)