Consider the following tasks shown in table below draw an


Resource : Information Technology Project management By kathy Schwalbe

Question One

Consider the following tasks shown in table below. Draw an Activity-on-Arrow (AOA) network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time

1297_Table.jpg

*All duration estimated times are in days; and the network proceeds from Node 1 to Node 9.

Question Two

Write all possible paths in the diagram of question one. What is the critical path for this project and how long is it?

Request for Solution File

Ask an Expert for Answer!!
Management Information Sys: Consider the following tasks shown in table below draw an
Reference No:- TGS02554704

Expected delivery within 24 Hours