Consider the following project activities their cost


Consider the following project activities, their cost, baseline time, actual time spent, and estimated time to completion:

Task     Estimated Cost per hour     Baseline Duration     Actual time spent     Estimated time to finish

A                $75                                     14 hr                      15 hr                         1 hr

Calculate the following project values showing your work:

  • Planned Value
  • Actual Cost
  • Earned Value
  • Schedule Variance
  • Cost Variance
  • Schedule Performance Index and
  • Cost Performance Index

Solution Preview :

Prepared by a verified Expert
Business Management: Consider the following project activities their cost
Reference No:- TGS02236104

Now Priced at $20 (50% Discount)

Recommended (92%)

Rated (4.4/5)