Consider the following activity-on-node aon pert project


Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity's completion time (in days) correspond to an optimistic time, most likely time, and pessimistic time, respectively. What is the probability of completing the project within 18 days?