Consider Table 6-2, Network Diagram Data for a Small Project.All duration estimates or estimates times are in days, and the network proceeds from Node 1 to Node 9.(Please answer the questions for Chapter 6, number 2 under Exercises, pp 246.)
| ACTIVITY |
INITIAL NODE |
FINAL NODE |
ESTIMATED DURATION |
| A |
1 |
2 |
2 |
| B |
2 |
3 |
2 |
| C |
2 |
4 |
3 |
| D |
2 |
5 |
4 |
| E |
3 |
6 |
2 |
| F |
4 |
6 |
3 |
| G |
5 |
7 |
6 |
| H |
6 |
8 |
2 |
| I |
6 |
7 |
5 |
| J |
7 |
8 |
1 |
| K |
8 |
9 |
2 |