Consider an activity with these estimates for optimistic


Consider an activity with these estimates for optimistic, most likely, and pessimistic time: 10, 17, 35.  Find the mean value of the activity time.  Consider an activity with these estimates for optimistic, most likely, and pessimistic time: 8, 18, 32.  Find the standard deviation of the activity time.

 

 