Consider a project which consists of the following set of


Consider a project which consists of the following set of activities: Activity Days Required Immediate Predecessor Activities A 3 -- B 4 A C 4 A D 3 A E 3 D F 4 B G 6 B H 5 F, C, E I 6 G, H J 4 F, C, E K 2 D L 6 I, J, K Draw the CPM network for this problem in Excel. Calculate the earliest and latest start and finish times, and the slack for each activity. Identify (Highlight) the critical path. Create a Gantt chart for this project in Excel. Remark: Please complete questions a, b, and c in Sheet 1 and question d in Sheet 2 of the same Excel file.