Consider a project having the following ten activities what


Question - Consider a project having the following ten activities:

Activity

Immediate Predecessors

Optimistic Time (o) (weeks)

Most likely Time (m) (weeks)

Pessimistic Timer (p) (weeks)

A

none

1

5

9

B

A

6

6

6

C

A

3

5

9

D

A

2

4

6

E

B, C

4

4

4

F

D

4

7

8

G

E

2

2

8

H

E, F

7

8

9

I

F

4

6

9

J

G, H, I

3

5

7

Required - What is the expected project completion time.