Consider a process consisting of three resources assume


Consider a process consisting of three resources. Assume there exists unlimited demand for the product.

Resource 1 has a processing time of 6 minutes per units.

Resources 2 has a processing time of 3 minutes per units.

Resource 3 has a processing time of 5 minutes per unit.

a. What is the capacity of resource2? _____ units/min

b. What is teh bottleneck in the process? ______ Resource

c. What is the utiliztion of resources 2? ____%

d. How long does it thake the process to produce 200 units starting with an empty system, assuming this is a worker-paced process? ______ minutes.