Conduct a discounted cash ow calculation to determine the


1. Conduct a discounted cash ?ow calculation to determine the NPV of the following project, assuming a required rate of return of 0.2. The project will cost $75,000 but will result in cash in?ows of $20,000, $25,000, $30,000, and $50,000 in each of the next four years.

2. In Problem 1, assume that the in?ows are uncertain but normally distributed with standard deviations of $1000, $1500, $2000, and $3500, respectively. Find the mean forecast NPV. What is the probability the actual NPV will be positive?