Computing the project completion time


Assignment:

Given is a PERT project network diagram as shown below.

1454_PERT project.JPG

Activity

Start

A

B

C

D

E

F

G

H

End

Time

0

3.35

1.35

3.15

1.89

5.14

3.65

2.18

1.89

0

a) The Project Completion time = _________ (in 2 decimal places)
b) The Earliest Start time, ES, of Activity G = ____________ (in 2 decimal places)
c) The Latest Finish time, LF, of Activity C =_____________ (in 2 decimal places)
d) The critical activities are =____________ (ex. type in critical activities as ABCD, no comma, no space)

Provide complete and step by step solution for the question and show calculations and use formulas.