Compute the variable overhead spending and efficiency


Cedar Key Company produces handmade clamming buckets and sells them to distributors along the Gulf Coast of Florida. The company incurred $9,400 of actual overhead costs ($8,000 variable; $1,400 fixed) in May. Budgeted standard overhead costs for May were $4 of variable overhead costs per direct labor hour and $1,500 of fixed overhead costs. Normal capacity was set at 2,000 direct labor hours per month. In May, the company produced 10,100 clamming buckets by working 1,900 direct labor hours. The time standard is 0.2 direct labor hour per clamming bucket.

Required: Compute the variable overhead spending and efficiency variances and (2) the fixed overhead budget and volume variances for May.

Solution Preview :

Prepared by a verified Expert
Cost Accounting: Compute the variable overhead spending and efficiency
Reference No:- TGS0806497