Compute the variable manufacturing overhead rate


Problem 10-15 Comprehensive Variance Analysis [LO1, LO2, LO3] Helix Company produces several products in its factory, including a karate robe. The company uses a standard cost system to assist in the control of costs. According to the standards that have been set for the robes, the factory should work 780 direct labor-hours each month and produce 1,950 robes. The standard costs associated with this level of production are as follows: Total Per Unit of Product Direct materials $ 35,490 $ 18.20 Direct labor $ 7,020 3.60 Variable manufacturing overhead $ 2,340 1.20 $ 23.00 During April, the factory worked only 760 direct labor-hours and produced 2,000 robes. The following actual costs were recorded during the month:

Total Per Unit of Product Direct materials $ 36,000 $ 18.00 Direct labor $ 7,600 3.80 Variable manufacturing overhead $ 3,800 1.90 $ 23.70 At standard, each robe should require 2.8 yards of material. All of the materials purchased during the month were used in production. Required: 1. Compute the materials price and quantity variances for April: (Input all amounts as positive values. Leave no cells blank - be certain to enter "0" wherever required. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect.

Round your intermediate calculations to 2 decimal places. Omit the "tiny_mce_markerquot; sign in your response.) Materials price variance $ Materials quantity variance $ 2. Compute the labor rate and efficiency variances for April: (Input all amounts as positive values. Leave no cells blank - be certain to enter "0" wherever required. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Round your intermediate calculations to 2 decimal places. Omit the "tiny_mce_markerquot; sign in your response.) Labor rate variance $ Labor efficiency variance $

3. Compute the variable manufacturing overhead rate and efficiency variances for April: (Input all amounts as positive values. Leave no cells blank - be certain to enter "0" wherever required. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Round your intermediate calculations to 2 decimal places. Omit the "tiny_mce_markerquot; sign in your response.) Variable overhead rate variance $ Variable overhead efficiency variance $

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Compute the variable manufacturing overhead rate
Reference No:- TGS0674860

Expected delivery within 24 Hours