Compute the total-price and quantity materials variances


Neville Company's standard materials cost per unit of output is $10 (2 pounds × $5). During July, the company purchases and uses 3,800 pounds of materials costing $19,570 in making 1,530 units of finished product. Compute the total, price, and quantity materials variances.