Compute the total overhead applied to production during may


Question:

I am having trouble with ch 4 problem 2 I'm hoping someone can lend a hand i need to plug n the numbers form the excel sheet for July into the question. Please look at numbers in the excel sheet they need to be inserted into the equation for July I am just not sure where they are supposed to go. 

Computations using a job order system

General Corporation employs a job order cost system. On May 1, the following balances were extracted from the general ledger:

Work in process $35,200
Finished goods 86,900
Cost of goods sold 128,700

Work in Process consisted of two jobs, No. 101 ($20,400) and No. 103 ($14,800). During May, direct materials requisitioned from thestoreroom amounted to $96,500, and direct labor incurred totaled $114,500. These figures are subdivided as follows:

Direct Materials Direct Labor
Job No. Amount Job No. Amount
101 $5,000 101 $7,800
115 19,500 103 20,800
116 36,200 115 42,000
Other   35,800 116 18,000
$96,500 Other    25,900
      $114,500

Job No. 115 was the only job in process at the end of the month. Job No. 101 and three "other" jobs were sold during May at a profit of20% of cost. The "other" jobs contained material and labor charges of $21,000 and $17,400, respectively.

General applies overhead daily at the rate of 150% of direct labor cost as labor summaries are posted to job orders. The firm's fiscal yearends on May 31.

Instructions

  1. Compute the total overhead applied to production during May.
  2. Compute the cost of the ending work in process inventory.
  3. Compute the cost of jobs completed during May.
  4. Compute the cost of goods sold for the year ended May 31.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Compute the total overhead applied to production during may
Reference No:- TGS02613949

Now Priced at $10 (50% Discount)

Recommended (97%)

Rated (4.9/5)