Compute the total cost of the potential job


A company has 2 categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows:

Maintenance $360,000

Inspection $750,000

The plant currently applies overhead using direct labor hours and expected capacity of 100,000 direct labor hours. The following data has been assembled for use in developing a bid for a proposed job. Bid prices are calculated as full manufacturing cost plus a 20% markup.

Direct materials: $2,210

Direct labor: $5,625

Machine hours: 450

Number of inspections: 4

Direct labor hours: 550

Total expected machine hours for all job during the year are 60,000, and the total expected number of inspections is 4,000.

Questions:

1. Compute the total cost of the potential job using direct labor hours to assign overhead.

2. Determine the bid price for the potential job.

3. Compute the total cost of the job using activity-based costing and the appropiate activity drivers.

4. Determine the bid price if activity-based costing is used.

5. Recommend a bid price for the potential job and support the recommendation by explaining which costing method best reflects the actial cost of the job.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Compute the total cost of the potential job
Reference No:- TGS0688756