Compute the takt time for a system where the total time per


Compute the takt time for a system where the total time per shift is 560 minutes, there is one shift, and workers are given two 18-minute breaks and 35 minutes for lunch. Daily demand is 326 units. (Round your answer to 2 decimal places.)

minutes per cycle