Compute the takt time for a system


Discuss the below in detail:

Q: Compute the takt time for a system where the total time per shift is 560 minutes, there is one shift, and workers are given two 13-minute breaks and 25 minutes for lunch. Daily demand is 322 units. (Round your answer to 2 decimal places.)

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Compute the takt time for a system
Reference No:- TGS02053404

Expected delivery within 24 Hours