Compute the sv cv and cpi for the project


Assignment: Project Planning - Schedule And Cost

When looking at the life of a project plan, it is useful to graph and outline the cost variance (CV), and schedule variance (SV). Determining progress, or lack of progress, provides essential information to assess a given project.

Complete exercise 2 in chapter 13 of the textbook. Given the data provided, in an excel spreadsheet, PowerPoint, or other appropriate method of delivery, determine the following:

1. Schedule Variance (SV)

2. Cost Variance (CV)

3. Schedule Performance Index (SPI)

4. Cost Performance Index (CPI)

In 250-300 words, answer the questions provided with the exercise. Reflect on the assessment of this project assessment. Should the project continue to improve?

Exercise 2 Question

On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51?

The response should include a reference list. Double-space, using Times New Roman 12 pnt font, one-inch margins, and APA style of writing and citations.

Solution Preview :

Prepared by a verified Expert
Project Management: Compute the sv cv and cpi for the project
Reference No:- TGS02129220

Now Priced at $40 (50% Discount)

Recommended (98%)

Rated (4.3/5)