Compute the schedule and cost variances for a project


Problem:

Find the schedule and cost variances for a project that has an actual cost at month 22 of $540,000, a scheduled cost of $523,000, and an earned value of $535,000.

What is your overall interpretation of this result?

Solve the problem and show all work.