Compute the pi statistic for project z if the appropriate


Compute the PI statistic for Project Z if the appropriate cost of capital is 7 percent. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project Z Time: 0 1 2 3 4 5 Cash flow –$3,000 $670 $800 $970 $620 $420 PI Should the project be accepted or rejected? Rejected Accepted

Request for Solution File

Ask an Expert for Answer!!
Financial Management: Compute the pi statistic for project z if the appropriate