Compute the payback period in years for the project if the


A project had and an initial outlay of $600 with the following Cash Flows: $370 in year 1, $165 in year 2, and $120 in year 3. Compute the payback period in years for the project if the discount rate was 12% (input number only and round to 2 decimal places like this 2.38)