Compute the payback period for a project with the following


1. Compute the payback period for a project with the following cash flows, if the company's discount rate is 14%. Initial outlay $460 Cash flow year 1 =$325 Cash flow year 2 = $75 Cash flow year 3 = $100

2. The risk-free rate, average returns, standard deviations, and betas for three funds and the S&P 500 are given below. Fund Avg Std Dev Beta A 18.50 % 36.50 % 1.35 B 18.00 % 31.00 % 1.10 C 16.00 % 25.50 % 1.15 S&P 500 11.00 % 20.00 % 1.00 rf 3.50 % What is the M2 measure for portfolio B?