Compute the npv statistic for project u if the appropriate


Compute the NPV statistic for Project U if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations.

Round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow -$1,550 $570 $2,030 -$630 $520 -$210 Should the project be accepted or rejected?