Compute the npv for project m if the appropriate cost of


Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)

Project M

Time: 0 1 2 3 4 5

Cash flow –$2,200 $590 $720 $760 $840 $340

NPV $

Should the project be accepted or rejected?