Compute the npv for project m if the appropriate cost of


Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)

Project M

Time: 0 1 2 3 4 5

Cash flow: –$1,900 $530 $660 $700 $780 $280

NPV $__________?

Request for Solution File

Ask an Expert for Answer!!
Financial Management: Compute the npv for project m if the appropriate cost of
Reference No:- TGS02403385

Expected delivery within 24 Hours