Compute the net present value of the proposed project


Antonio Melton, the chief executive officer of Baird Corporation, has assembled his top advisers to evaluate an investment opportunity. The advisers expect the company to pay $416,000 cash at the beginning of the investment and the cash inflow for each of the following four years to be the following: Year 1 Year 2 Year 3 Year 4 $ 91,000 $ 101,000 $ 128,000 $ 191,000 respectively. Mr. Melton agrees with his advisers that the company should use the discount rate (required rate of return) of 10 percent to compute net present value to evaluate the viability of the proposed project. (PV of $1 and PVA of $1) (Use appropriate factor(s) from the tables provided.)

Required

a. Compute the net present value of the proposed project. Should Mr. Melton approve the project? (Negative amounts should be indicated by a minus sign. Round your intermediate calculations and final answer to the nearest whole dollar.)

b. &c. Shawn Love, one of the advisers, is wary of the cash flow forecast and she points out that the advisers failed to consider that the depreciation on equipment used in this project will be tax deductible. The depreciation is expected to be $83,200 per year for the four-year period. The company’s income tax rate is 35 percent per year. Use this information to revise the company’s expected cash flow from this project. Compute the net present value of the project based on the revised cash flow forecast. Should Mr. Melton approve the project? (Negative amount should be indicated by a minus sign. Round your intermediate calculations and final answer to the nearest whole dollar.)

Request for Solution File

Ask an Expert for Answer!!
Financial Management: Compute the net present value of the proposed project
Reference No:- TGS02677467

Expected delivery within 24 Hours