Problem: During the last quarter, BOSE Corp. recorded the following average times per order received and processed:
Wait time to start production….         9.0 days
Inspection time…..                           0.8 days
Process time…                                 3.0 days
Move time…                                     0.2 days
Queue time…                                   6.0 days
a. Compute the throughput time. 
Throughput time =
b. Compute the manufacturing cycle efficiency (MCE)
MCE = 
c. What percentage of the production time is spent in non value added activities?
d. Compute the delivery cycle time. 
Delivery cycle time =