Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)

Project E

Time:           0         1      2       3     4       5

Cash flow –$2,000 $750 $780 $720 $500 $300

IRR %

Should the project be accepted or rejected?