Compute the expected time or duration for each activity the


Project path A-C-E-J has these activity time estimates in days:

Activity                 Optimistic                   Most Likely                Pessimistic

A                            3                                  4                                 5

C                            9                                 12                               14

E                            12                                15                               20

J                             7                                  9                                9

Compute the expected time or duration for each activity, the variance for each activity, and the expected duration and variance for the path.