Compute the economic order quantity and the reorder point


Discussion Post: Managing Operations

The manager at the Challenger store in Clementi is planning for the inventory of their printers. Average demand for the printers is 50 units per day, ordering cost is $50 per order, unit price is $100, lead-time is 2 weeks, carrying/holding rate is 20%, and standard deviation of demand is 20 units per day. Consider 365 days per year. Assume the manager uses a fixed order quantity system. Compute the economic order quantity and the reorder point to have 90% service level. Explain your result.

The response must include a reference list. Using one-inch margins, double-space, Times New Roman 12 pnt font and APA style of writing and citations.

Solution Preview :

Prepared by a verified Expert
Operation Management: Compute the economic order quantity and the reorder point
Reference No:- TGS03076566

Now Priced at $15 (50% Discount)