Compute the direct materials price variance and the direct


Question - Puffy Parkas, Inc. manufactures designer parkas. The company uses standard costing and has developed the following information about standards for its product:

per unit;

Material: 3 yards per unit; $15 per yard

Labor: 0.4 DL hours per unit; $9 per hour

During November, the company experienced an unanticipated spike in demand and increased production. Although planned production was for 1,200 units, the company actually produced 1,500 units.

In anticipation of the original production volume, 3,600 yards were purchased, at a total cost of $55,000. During the month, 4,400 yards of material were used, and 610 direct labor hours were worked. Direct labor cost for the month totaled $5,551.

Compute the direct materials price variance and the direct material quantity variance and specify if each is favorable or unfavorable.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Compute the direct materials price variance and the direct
Reference No:- TGS02583833

Now Priced at $25 (50% Discount)

Recommended (91%)

Rated (4.3/5)