Compute the cm per unit of capacity machine-hour for each


Question - You produce armor kits for military vehicles. Due to a recent expansion of the war on terror to an unnamed new country, the demand for your products is booming, and you do not have enough capacity to fully fill the demand. You offer 3 versions of the product, Basic, Premium and Supreme, which offer different levels of protection. The demand and cost information is as follows:


Basic

Premium

Supreme

Demand (units)

6,000

3,000

1,500

Price/unit

$1,200

$2,000

$4,000

Unit VC

$400

$600

$1,200

Machine hours per unit

1

1.5

4

Required:

(a) Compute the CM per unit of capacity (machine-hour) for each product?

(b) Based on your answer in (a), how much of each product should you produce?

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Compute the cm per unit of capacity machine-hour for each
Reference No:- TGS02844822

Now Priced at $25 (50% Discount)