Compute the average flow time tardiness and lateness for


An insurance claims work area has five claims waiting for processing as follows:
Job A: process time: 15 Due date: 26
Job B: process time: 21 Due date: 32
Job C: process time: 20 Due date: 35
Job D: process time: 10 Due date: 30
Job E: process time: 12 Due date: 23

Compute the average flow time, tardiness, and lateness for the following sequences: SPT sequence, EDD sequence, and sequence B-A-E-C-D

What sequencing rule do you recommend and why?

 

Request for Solution File

Ask an Expert for Answer!!
Finance Basics: Compute the average flow time tardiness and lateness for
Reference No:- TGS0619003

Expected delivery within 24 Hours