Compute the average cycle time and normal time for each


Decision Sceince Institute (DSI) promotes its annual national conference by mailing thousands of letters to various recipients. A time study has been conducted on the task of preparing the letters for mailing. On the basis of the observations below, DSI wants to develop a time standard for the task. The organization's personal, delay, and fatigue allowance factor is 15 percent. Compute the average cycle time and normal time for each element. Then calculate the standard time for the entire task.

Cycle Ovserved in Minutes
Job Element 1 2 3 4 5 Performance Rating
(A) 8 10 9 11 11 120%
(B) 2 3 2 1 3 105%
(C) 2 1 3 2 1 110%

Job Element Description:
(A) Complose Letter
(B) Print Address Labels
(C) Stuff, Seal and Sort Envelopes

 

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Compute the average cycle time and normal time for each