Compute npv and irr for each project rank the projects from


Instructions

1.  Compute NPV and IRR for each project.

2.  Rank the projects from 1 to 8 with 1 being the best project

3.  If necessary or desired you can provide further computations or explanation under the rankings.

Discount Rate 10.00%

The Investment Detective

               

Year

1

2

3

4

5

6

7

8

0

(2000)

(2000)

(2000)

(2000)

(2000)

(2000)

(2000)

(2000)

1

330

1666

 

160

280

2200

1200

(350)

2

330

334

 

200

280

 

900

(60)

3

330

165

 

350

280

 

300

60

4

330

   

395

280

 

90

350

5

330

   

432

280

 

70

700

6

330

   

440

280

   

1200

7

330

   

442

280

   

2250

8

1000

   

444

280

     

9

     

446

280

     

10

     

448

280

     

11

     

450

280

     

12

     

451

280

     

13

     

451

280

     

14

     

452

280

     

15

   

10000

(2000)

280

     

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Compute npv and irr for each project rank the projects from
Reference No:- TGS01283600

Now Priced at $10 (50% Discount)

Recommended (98%)