Compute forecast using exponential smoothing


Problem:

WEEK OF PINTS USED

August 31 360

September 7 389

September 14 410

September 21 381

September 28 368

October 5 374

Required:

i) Forecast the demand for the week of October 12 using a 3-week moving average.

ii) Use a 3-week weighted moving average, with weights of .1, .3, and .6, using .6 for the most recent week. Forecast demand for the week of October 12.

iii) Compute the forecast for the week of October 12 using exponential smoothing with a forecast for August 31 of 360 and a 5 .2.

Carefully solve the numerical problem and show all the steps of calculation.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Compute forecast using exponential smoothing
Reference No:- TGS0877486

Expected delivery within 24 Hours