Compute effectiveness of rule using average completion time


The following table shows orders to be processed at a machine shop as of 8:00 a.m. Monday. The jobs have different operations they must go through. Processing times are in days. Jobs are listed in order of arrival.

ob Processing
Time (Days)
Due Date
(Days)
Remaining Number
of Operations
A 8         20 2
B 10         18 4
C 5         25 5
D 11         17 3
E 9         35 4

Required:

Question 1) Determine the processing sequence at the first work center using each of these rules: (1) First come, first served, (2) Slack per operation.

Question 2) Compute the effectiveness of each rule using each of these measures: (1) average completion time, (2) average number of jobs at the work center. Solve the given numerical problem and illustrate step by step calculation.