Compute all manufacturing overhead variances for layt -


Layt Clock Company has developed the following flexible budget for its overhead costs. Manufacturing overhead at Layt is applied to production on the basis of standard machine-hours:


Machine Hours


21,600

24,000

26,400

Clocks produced

18,000

20,000

22,000

Variable overhead cost

$127,440

$141,600

$155,760

Fixed overhead cost

$171,072

$171,072

$171,072

Layt was expecting to produce 22,000 clocks last year. The actual results for the year were as follows:

Number of clocks produced

21,500

Machine-hours incurred

24,940

Variable overhead cost

$145,899

Fixed overhead cost

$170,540

Required:

Compute all four manufacturing overhead variances for Layt.

Solution Preview :

Prepared by a verified Expert
Managerial Accounting: Compute all manufacturing overhead variances for layt -
Reference No:- TGS0787055

Now Priced at $40 (50% Discount)