Compute a simple exponential smoothing forecast for week 7


The actual demand of the patients at Omaha Emergency Medical clinic for the first six weeks of the year are as follows:

week Actual # of patients

1 65

2 62

3 70

4 48

5 63

6 52

a.) Compute a simple exponential smoothing forecast for week 7 with a=5. Assume the forecast for week 1 is 65.

 