Compute a predetermined overhead rate for mcdougal


McDougal Company uses a predetermined overhead rate to assign overhead to jobs. Because McDougal's production is machine intensive, overhead is applied on the basis of machine hours. The expected overhead for the year was 2.8 million and the practical level of activity is 250,000 machine hours.

During the year, McDougal used 255,000 machine hours and incurred actual overhead costs of 2.82 million. McDougal also had the following balances of applied overhead in its accounts:

  • Work-in-process inventory 192,000
  • Finished goods inventory 208,000
  • Cost of goods sold 600,000

Required:
1) Compute a predetermined overhead rate for McDougal.
2) Compute the overhead variance, and label it as under- or overapplied.
3) Assuming the overhead variance is immaterial, prepare the journal entry to dispose of the variance ant the end of the year.
4) Assuming the overhead variance is material, prepare the journal entry that appropriately disposes of the overhead variance at the end of the year.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Compute a predetermined overhead rate for mcdougal
Reference No:- TGS0704564

Expected delivery within 24 Hours