Using the solution from Problem 5 and given the list of crash times and costs, determine the new diagram and times.
Assume for every day you complete the project ahead schedule you recieve a $60 bonus payment.
Question 5 Solution:
Critical Path = ABDFG Total Project Time = 42
| PERT Time |
| 11 |
| 8 |
| 6 |
| 8 |
| 10 |
| 4 |
| 11 |
|
|
Total Cost |
|
|
|
Maximum |
| Activity |
Normal |
Crash |
Normal |
Crash |
Reduction |
| A |
11 |
4 |
150 |
550 |
7 |
| B |
8 |
3 |
300 |
450 |
5 |
| C |
6 |
6 |
600 |
750 |
0 |
| D |
8 |
4 |
100 |
100 |
4 |
| E |
10 |
5 |
650 |
680 |
5 |
| F |
4 |
1 |
750 |
945 |
3 |
| G |
11 |
2 |
225 |
300 |
9 |
Total Crash Costs =
New Crashed Project Time =