Complete the mrp schedule for the product below product a


Complete the MRP schedule for the product below. Product A Lot Size = 75 Safety Stock = 50 Lead Time = 1 week Allocated = 100 in hand =300 WEEKS 1 2 3 4 5 Gross requirement 500 700 400 500 Scheduled receipt 600 Available on hand 300+600-100-50=750 Net requirements Planned order receipts Planned order releases

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Complete the mrp schedule for the product below product a
Reference No:- TGS01506630

Expected delivery within 24 Hours