Complete the dependency column of the table and include the


Classroom Exercise: Small Decorating Project

Activity ID

Description

Duration (days)

Dependency(ies) and Type (FS, SS, SF, FF)

1

Decorate Room (Summary Task)

-

-

2

Remove furnishings

1

 

3

Fetch Paint

1

 

4

Fetch wallpaper

1

 

5

Strip walls

4

 

6

Paint ceiling and woodwork

2

 

7

Hang wallpaper

5

 

8

Replace furnishings

1

 

9

Tidy up, relax and brag about your DIY skills

1


Using the activity table above:

Complete the Dependency column of the table and include the dependencies and types of dependency for each activity

Produce a Project Schedule Network diagram for the project

Produce a critical path method diagram and identify the critical path of the project.

Determine the maximum project duration, assuming two units of resource that you may allocate however you wish
Produce a Gantt chart Key:

FS: Finish to Start: activity can only start when predecessor is finished regardless of resource availability SS: Start to Start: Activity and its predecessor may start simultaneously if resources are available

SF: Start to Finish: Activity must finish before predecessor may start

FF: Finish to Finish: Activity must finish at the same time as its predecessor

Solution Preview :

Prepared by a verified Expert
HR Management: Complete the dependency column of the table and include the
Reference No:- TGS01400220

Now Priced at $20 (50% Discount)

Recommended (98%)

Rated (4.3/5)