Complete information required to prepare a partial balance


In 2013, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2015. Information related to the contract is as follows:


2013 2014 2015
  Cost incurred during the year $ 2,291,000
$ 3,555,000
$ 2,259,400
  Estimated costs to complete as of year-end
5,609,000

2,054,000

0
  Billings during the year
1,900,000

3,946,000

4,154,000
  Cash collections during the year
1,710,000

3,500,000

4,790,000

Westgate uses the percentage-of-completion method of accounting for long-term construction contracts.

1. Calculate the amount of gross profit (loss) to be recognized in each of the three years.

2.1 In the journal below, complete the necessary journal entries for the year 2013 (credit various accounts for construction costs incurred).

2.2 In the journal below, complete the necessary journal entries for the year 2014 (credit various accounts for construction costs incurred).

2.3 In the journal below, complete the necessary journal entries for the year 2015 (credit various accounts for construction costs incurred).

3. Complete the information required below to prepare a partial balance sheet for 2013 and 2014 showing any items related to the contract.

4.

Calculate the amount of gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations.)

  

2013 2014 2015
  Costs incurred during the year $ 2,510,000
$ 3,855,000
$ 3,210,000
  Estimated costs to complete as of year-end
5,710,000

3,210,000

0

  5. Calculate the amount of gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations.)


2013 2014 2015
  Costs incurred during the year $ 2,510,000
$ 3,855,000
$ 4,065,000
  Estimated costs to complete as of year-end
5,710,000

4,210,000


Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Complete information required to prepare a partial balance
Reference No:- TGS0680690

Expected delivery within 24 Hours