Complete a project task analysis during which the project


Complete a project task analysis, during which the project mission, goal, objectives, and approach developed in Week Two are further broken down into a hierarchical WBS at the second or third level. The final assignment is due in Week Five.

Complete items 7 through 10 of the components described for the written report in Week One.

Arrange second-level WBS elements (tasks) in the form of a task-flow network, using PERT or CPM techniques, to illustrate the earliest completion time, task, dependencies, and the critical path.

Illustrate scheduled start and completion times for each second-level WBS task on a timeline in the form of a Gantt chart. Use Microsoft Project.

Request for Solution File

Ask an Expert for Answer!!
Project Management: Complete a project task analysis during which the project
Reference No:- TGS01035019

Expected delivery within 24 Hours