Chris received new word processing software for her


Chris received new word processing software for her birthday. She also received a check, with which she intends to purchase a new computer. Chris’s college instructor assigned a paper due next week. Chris decided that she will prepare the paper on the new computer. She made a list of the activities she will need to do and their estimated times.

c. Determine the critical path and the expected duration time.

d. What are some possible reasons for the project to take longer than the expected duration? Use Excel for both and the critical path method on c.

Estimated Time (hrs.) Activity (abbreviation)

0.8 Install software (Inst)

0.4 Outline the paper (Out)

0.2 Submit paper to instructor (Sub)

0.6 Choose a topic (Ch)

0.5 Use grammar-checking routine andmake corrections (Ck)

3.0 Write the paper using the word-processing software (Write)

2.0 Shop for a new computer (Sh)

1.0 Select and purchase computer (Sel)

2.0 Do library research on chosen topic (Lib)